Looking to modify or relocate an existing transmission facility?
Modification Process
Understand the modification process below before applying.
Processing Time: 7 calendar days
Submit a Transmission Facility Modification Request Application complete with all required information. Once we’ve received it, we’ll notify you.
Processing Time: 15 calendar days
We’ll review the Transmission Facility Modification Request Application. If information is missing, you must provide it before we can advance the request to the next stage. We may meet with you in this stage to ensure the scope of the project is understood.
Processing Time: 120 calendar days
We complete a Facility Modification Assessment to identify potential options, estimated costs, and a target in-service date for the modification. You’ll review the assessment and decide whether to proceed or cancel the request. We’ll also facilitate a meeting to review the assessment with you.
Please note: If you accept the cost estimate defined in this assessment, you don’t need to complete stage 4.
You’ll enter into a Definition Phase Agreement, where we’ll produce a Definition Phase Summary Report. You’ll review the report and decide to proceed with a Cost Recovery Agreement or cancel the request.
You’ll enter into a Cost Recovery Agreement with us for the construction and associated costs of the work required.
Construction activities begin.
Project enters construction and both parties fulfill their obligations to meet the in-service date. Final invoicing is based on actual construction costs.
Ready to Get Started?
Review the process diagram and fill out the application form. Once completed, email us.